ach_xx

Improved performance of a production line

Responsible for definition of the process and procedures including their implementation on the new automated factory investment in the production facility at Fradley Park.


Liaising with operations and translating their requests to a professional technical language used in discussions with original equipment manufacturers to improve the production process. Saved 15-20k in remote support hours costs per month, resulting in approx. 200k per year.

RapidImprovement_progress_sm
20190704_100400
20190313_144827
20190603_171801
20190409_103918

Project statistics:


  • 6 OEM suppliers
  • 12 Siemens S7-1500 controllers
  • Engineering stations running WinCC 7.4
  • All equipment networked through Profinet and WiFi for mobile devices
  • PC terminals for every working station including forklifts
  • Successfully finish commissioning phase with OEMs

  • Improved production line output from 20% to 70%

  • Prepared strategy for further improvements

                  of control systems including data acquisition